Outbuildings: Week 36, Day 4

Outbuildings: Week 36, Day 4

The main progress today was more second-fix of the alarm system, where most of the physical installation was completed – with the exception of the magnetic contact on one of the roller shutters, because the controller isn’t responding and the door is stuck open (that will get attention from the installers tomorrow) and the radio link to the alarm system in the House.

The automatic reader for the various M-Bus meters was also installed, now the data network is operational.

Outbuildings: Week 36, Day 3

Outbuildings: Week 36, Day 3

Wet weather again but no major issue for indoor work. The electrical installation team were back to finish up the last of their testing and fit the two myenergi Zappi car chargers.

The alarm installer is due back tomorrow which prompted some final preparations for installing the last of the alarm keypads, now the (internal) conduit for the outdoor lighting has been fitted.