Outbuildings: Week 28, Day 3

Outbuildings: Week 28, Day 3

Lots of rain overnight and throughout the morning, resulting in the large puddle visible in the Courtyard (and the pond elsewhere on the site that’s been dry for months is now holding a little water).

Given the weather, the build team concentrated on indoor work – installing plasterboard on the ceiling of the Workshop, which is roughly 2/3 complete.

The digger and dumper truck that will be used for excavating the drains in the Courtyard were delivered, but not used yet.

Outbuildings: Week 28, Day 2

Outbuildings: Week 28, Day 2

Completion of the installation of the main set of windows and doors and also the installation of the ridge tiles on the roof over the Garages (taking advantage of a day of dry and not particularly windy weather).

Three-leaf bifold door installed between the single Garage (pictured) and the end of the Workshop
Roofing now completed over the Garages, following the installation of the Ridge Tiles with a dry-fix ventilated ridge kit made by Timloc