No build progress on site today.
A decent day for solar generation though, peaking at 10 kW at noon.

No build progress on site today.
A decent day for solar generation though, peaking at 10 kW at noon.

More tidying-up of the site and completing a few outstanding jobs inside but mostly finishing off the temporary, shallow ramp that provides access to the block-paved parking area. That needed two lorry-loads of recycled aggregate, on top of the larger-sized stone installed yesterday.

This is ‘temporary’ in as much as nothing more permanent was included in the scope of the build contract. In due course some block paving will be brought further towards the House, but the extent of that paving and the choice of materials is part of the wider landscaping scheme for which the design is not yet confirmed. Overall it’s quite a large, flat area that could probably do with breaking up with some planting – perhaps in containers?
The digger, dumper and roller used for the drainage and driveway works have been off-hired and will be collected early next week.
This marks the end of the main work for the prime contractor but there’s still some subcontract work to complete:
There are also a few items of work not included in the main build contract:
It’s therefore close to the time when it’s appropriate to suspend these regular daily updates. For now, my thinking is to leave them running until the Architect declares ‘practical completion’ and Building Control are ready to issue their final certificate, which will probably be another week or two. I might delete the daily updates on days when there’s nothing to report.