Week 55, Day 5

Week 55, Day 5:

  • More tidying up of the site, most notably stacking the waste wood to make a bonfire for Bonfire Night
  • Some minor re-grinding of the polished concrete floor to remove a few scratches and even things up around one of the recessed floor boxes, followed by an overall re-sealing and re-buffing of all the polished concrete areas
  • A delivery of concrete blocks for the retaining wall
Week 55, Day 5

Week 55, Day 5

Bonfire from waste wood, old pallets etc.

Bonfire from waste wood, old pallets etc.

Week 54, Day 2

Week 54, Day 2:

  • Installation of the Phone Line into the house, using the armoured cable previously routed from the Comms room to the underground joint box outside
    • This isn’t operational yet due to a fault on the line between the Distribution Point and the Cabinet which should be fixed within a day or two
  • Laying the rubber tiles over their underlay on the balcony
    • These are Eurodec Premier Rubber Tiles in grey which protect the Sarnafil single-ply membrane beneath while allowing water to drain though
Week 54, Day 2

Week 54, Day 2

Eurodec Premier Rubber Tiles on balcony floor

Eurodec Premier Rubber Tiles on balcony floor