Week 37, Day 3

Week 37, Day 3:

  • More plastering
  • More electrical and plumbing first-fix, including a lot of work in the Plant Room
  • Forming the dropped-ceiling in the ground floor shower room
Week 37, Day 3

Week 37, Day 3

DHW tank (left) and GSHP unit (right) installed in the Plant Room

DHW tank (left) and GSHP unit (right) installed in the Plant Room

Acoustic rubber pad under GSHP

Acoustic rubber pad under GSHP

Framework for dropped-ceiling in ground floor shower room

Framework for dropped-ceiling in ground floor shower room

 

Week 35, Day 5

Week 35, Day 5:

  • The “south” camera has been going offline occasionally (maybe it’s all the rain?) and as a result there are no time-lapse photos from that camera today, so here’s one from the “north” camera instead
  • More plastering on the Second Floor, including skimming the ceiling in the Office
  • More progress with the pipework for the Ground Source Heat Pump in the Plant Room
Week 35, Day 5

Week 35, Day 5

Plaster skim coat complete on the Office ceiling

Plaster skim coat complete on the Office ceiling

Pipework progressing in the Plant Room

Pipework progressing in the Plant Room