More tidying up of the stormwater drainage around the outside of the buildings – and a lot of filling lorries removing excess excavated soil from site.

More tidying up of the stormwater drainage around the outside of the buildings – and a lot of filling lorries removing excess excavated soil from site.

Inspection by Building Control early in the day which confirmed they were happy with the drain layouts so those are now partially back-filled – initially with pea shingle then (in some places) with excavated material.
Further work to prepare the drainage connections for the rainwater downpipe connections.