Week 44, Day 2

Week 44, Day 2:

  • Installing the oak into the lids of the floor-boxes in the Living Room
  • Installing some of the internal wooden window boards, which match the wood on the inside of the windows
  • More work on hanging internal doors and installing door furniture
Week 44, Day 2

Week 44, Day 2

Completed floor-box lid, prior to sanding

Completed floor-box lid, prior to sanding

Internal window boards in Living Room

Internal window boards in Living Room

Door to En-Suite in Bedroom 3

Door to En-Suite in Bedroom 3

Week 44, Day 1

Week 44, Day 1:

  • Installing the replacement Silestone worktop for the island in the kitchen
  • Lots more work on skirting boards, architraves and internal doors
  • Preparing the boards for the internal window sills
Week 44, Day 1

Week 44, Day 1

Island worktop in kitchen

Island worktop in kitchen

Skirting boards in Bedroom 4

Skirting boards in Bedroom 4

Boards being edge-glued with biscuits for the window sills