Week 41, Day 4

Week 41, Day 4:

  • More second-fix electrical, including the installation of some of the LED down-lighters
  • More work on the kitchen, including installing the fridge, the main sink, sorting out the placement of the taps and the pop-up sockets and having Midland Stone Centre measure up for the worktops which should be ready in a week
  • More finishing up on the balcony, cladding the walls in cedar
    • Now that I come to check the photo some of the boards have been stored wet, have discoloured and will need to be replaced
  • More plastering in the Living Room
Week 41, Day 4

Week 41, Day 4

One of the LED down-lighters

One of the LED down-lighters (SPOT from BPM Lighting)

Main sink in the kitchen

Main sink in the kitchen, made by BLANCO

 

Cedar cladding around the balcony

Cedar cladding around the balcony

Week 40, Day 4

Week 40, Day 4:

  • Floor tiling in the bathrooms – the tiles are now installed in about half of the rooms
  • Delivery of the appliances for the kitchen ready for those to be installed next week
  • Tidying up the external corners on the cedar cladding
  • More plastering in the ground-floor rooms
  • More second-fix electrical, preparing some of the connections in the Plant Room
    • There’s now power to some of the circuits, including the PIR-switched lights in the Plant, Comms and Storage Rooms on the Second Floor
Week 40, Day 4

Week 40, Day 4

Floor tiles (without grout yet) in the Second-Floor Bathroom

Floor tiles (without grout yet) in the Second-Floor Bathroom

Floor tiling (without grout yet) in the En-Suite for Bedroom 3

Floor tiling (without grout yet) in the En-Suite for Bedroom 3

Finishing touches to the cedar cladding at the external corners

Finishing touches to the cedar cladding at the external corners