Week 49, Day 1

Week 49, Day 1:

  • Work to install the cove moulding (between the top of the walls and the ceiling) in the Living Room which will house LED strip lights as the main source of lighting for the room – one strip is at the “top” of the moulding – lighting across the ceiling – and another is at the “bottom” – lighting down the walls
    • We’d been aware for a while that the Living Room ceiling wasn’t flat but the coving showed up just how not-flat it is, and for the LED strip lights to work well the coving needs to fit tight against the wall and the ceiling. Some re-work on the ceiling will be required.
  • Lots of commissioning of the plumbing systems – pressure-testing and checking for correct operation. The water is now “on” but the drains aren’t connected up yet.
  • Preparation for machining the oak treads for the staircases, ensuring that the slight inconsistencies between the locations of the supporting steel treads will be adjusted out when the oak goes on
  • At the weekend I commissioned one set of temperature monitors (portable units from Oregon Scientific) and configured the software to collect the temperature details in a “Time Series Database” (InfluxDB) and I’ve been experimenting with various tools for graphing the outputs, my current favourite being Grafana – sample image below
    • I’ve started drafting some more notes on this which I’ll publish as a Technical Article in due course
    • The most notable conclusion from the data collected so far is that the second floor is much warmer than the ground floor – not really a surprise since it’s very evident when working in the house, and hot air rises… – when the MVHR is running the temperatures will even out considerably
    • The Comms Room has some IT kit generating a few watts of heat and hence it is (even) warmer than the Plant Room, also on the Second Floor
Week 49, Day 1

Week 49, Day 1

Living Room Coving

Living Room Coving – Needs Work…

Grafana Temperature Dashboard

Grafana Temperature Dashboard

Week 47, Day 4

Week 47, Day 4:

  • Quite a lot of time spent tidying and cleaning the rooms which are nearly finished
  • More second-fix electrical:
    • Work in the Plant Room, hooking up the supply to the Ground Source Heat Pump and the heating zone valves and circulation pumps
    • Work on the ground floor, wiring in the DALI-dimmable LED drivers for the kitchen and open plan dining area
Week 47, Day 4

Week 47, Day 4

Heating circulation pumps - pipes need insulating

Heating circulation pumps – pipes need insulating

BPM Aquilae lights in the Open Plan area

BPM AQUILAE lights in the Open Plan area

These lights are 9.6W LEDs running at 500mA constant current. The hole in the middle is for a ceiling loudspeaker.