Week 47, Day 4

Week 47, Day 4:

  • Quite a lot of time spent tidying and cleaning the rooms which are nearly finished
  • More second-fix electrical:
    • Work in the Plant Room, hooking up the supply to the Ground Source Heat Pump and the heating zone valves and circulation pumps
    • Work on the ground floor, wiring in the DALI-dimmable LED drivers for the kitchen and open plan dining area
Week 47, Day 4

Week 47, Day 4

Heating circulation pumps - pipes need insulating

Heating circulation pumps – pipes need insulating

BPM Aquilae lights in the Open Plan area

BPM AQUILAE lights in the Open Plan area

These lights are 9.6W LEDs running at 500mA constant current. The hole in the middle is for a ceiling loudspeaker.

Week 47, Day 2

Week 47, Day 2:

  • Lots more work on the second-fix electrical, including the light fittings and drivers in the kitchen and the control panels for the ground floor
  • Further work on the interior woodwork (window sills) and door furniture
Week 47, Day 2

Week 47, Day 2

BPM AQUILAE recessed LED downlight in kitchen

BPM AQUILAE recessed LED downlight in kitchen

Control panels mostly complete for the Ground Floor

Control panels mostly complete for the Ground Floor