Week 39, Day 3 Posted on 2016-07-13 by dMb Reply Week 39, Day 3: Preparing for the waterproofing of the first-floor balcony, insulating the structural steel column and covering the insulation with plywood; it will get clad in zinc later More plastering More electrical second-fix Week 39, Day 3
Week 39, Day 2 Posted on 2016-07-12 by dMb Reply Week 39, Day 2: More plastering More second-fix plumbing and electrical, cutting out holes for the down-lights and PIR sensors (used in bathrooms and on landings) Completing the external insulation of the SIPS panels around the clerestory windows Week 39, Day 2