Week 38, Day 4

Week 38, Day 4:

  • Another day with a significant change visible from the time-lapse camera – the standing-seam zinc roof covering has started going on the south roof
  • Second-fix has started for the electrical installation, with mains sockets now installed on the second floor and the 9u, 19″ communications equipment rack mounted on the wall in the Comms Room on the second floor
  • More wet plastering, aiming to get the bathrooms ready for sanitaryware and tiling next week
Week 38, Day 4

Week 38, Day 4

Zinc roof installation underway

Zinc roof installation underway

Closer view of the zinc roofing status at the end of the day

Closer view of the zinc roofing status at the end of the day

Mains sockets in the home office on the second floor

Mains sockets in the home office on the second floor

Network communications cabinet mounted on the wall of the Comms Room

Network communications cabinet mounted on the wall of the Comms Room

Week 38, Day 2

Week 38, Day 2:

  • The team from Contrasol were back on site to install the steel support brackets for the brise soleil
    • The large expanse of glazing on the south elevation in particular is good for natural light and passive solar gain in the winter but potentially introduces a risk of overheating in the summer
    • A horizontal brise soleil just above the sliding doors blocks the high-level sun in mid summer but allows the lower winter sun through underneath
    • The exact projection of the brise soleil was included in the PHPP calculations to take account of both the passive solar gain and the risk of overheating
  • The first of the wet plaster on the masonry walls
    • Almost all of the rooms have at least one masonry wall
    • The external walls are wet-plastered to form the main air tightness barrier
    • While the internal masonry walls could be plasterboarded (with dot-and-dab fixings) most of them are also wet plastered, which is better for thermal mass
Week 38, Day 2

Week 38, Day 2

Steel support brackets for Contrasol brise soleil above sliding doors on the south and west elevations

Steel support brackets for Contrasol brise soleil above the sliding doors on the south and west elevations

Base coat of wet plaster on the masonry outer wall in Bedroom 3

Base coat of wet plaster on the masonry outer wall in Bedroom 3

Finish coat of wet plaster on an internal masonry wall in Bedroom 3

Finish coat of wet plaster on an internal masonry wall in Bedroom 3