Week 36, Day 3

Week 36, Day 3:

  • More plasterboard dry-lining
  • More skimming of the plasterboard on the second floor (notably the curved roof over the staircase)
  • Building out the wooden framework for the south wall in the open-plan area
  • More electrical first-fix, mostly the recessed wall lights in the hall and landing
Week 36, Day 3

Week 36, Day 3

Dry lining in the family bathroom

Dry lining in the family bathroom

Completed plaster skim coat over the staircase

Completed plaster skim coat over the staircase

Timber framework on the south wall of the open plan area

Timber framework on the south wall of the open plan area

Week 36, Day 2

Week 36, Day 2:

  • A specialist dry-lining team have been on-site all day, boarding the ceilings and other areas which are being dry-lined
  • The normal plasterers have been working on the curved roof over the staircase
  • The rest of the team have continued preparing for the plastering on the ground floor
Week 36, Day 2

Week 36, Day 2

Starting the dry-lining of the sloping ceiling over the Master Bedroom

Starting the dry-lining of the sloping ceiling over the Master Bedroom

Base coat of plaster on the curved roof over the staircase

Base coat of plaster on the curved roof over the staircase

One of the "Fylo" recessed strip lights boarded in place and ready for the skim coat

One of the “Fylo” recessed strip lights boarded in place and ready for the skim coat