
No work on site today since it’s the Good Friday Public Holiday, but leaving this photo in place to show how the floor slab is curing (it’s a bit paler than yesterday).

No work on site today since it’s the Good Friday Public Holiday, but leaving this photo in place to show how the floor slab is curing (it’s a bit paler than yesterday).

After some uncertainty about the weather (which was windy but much less wet than had been forecast a few days previously) the installation of the concrete floor slabs went ahead as planned.
The concrete pump was all set-up and ready by 07:00 then four lorry-loads of concrete were delivered and laid between 08:30 and 11:30.

The specification called for a power-floated finish so a team from UK Concrete Flooring Specialists Ltd were kept busy finishing the surface until sunset.
