Week 43, Day 3:
- The main finishing touches on the zinc roofing, with just the down-pipes left to install
- This included the installation of the two roof windows which have been on-site since mid-February
- More work on the external window reveals and sills
- More second-fix electrical, mostly sockets and switches on the first floor
- More second-fix plumbing, mostly installing the “wet room” (i.e. recessed into the floor) shower tray in the ground-floor shower room
- Mostly completing the installation of the engineered oak flooring in the Living Room, with just the circular in-lays in the floor box lids to complete
- Filling and sanding the recessed plaster down-lights in the open plan area in preparation for painting the ceiling
- Starting to commission the computer network and WiFi Access Points