Week 36, Day 2

Week 36, Day 2:

  • A specialist dry-lining team have been on-site all day, boarding the ceilings and other areas which are being dry-lined
  • The normal plasterers have been working on the curved roof over the staircase
  • The rest of the team have continued preparing for the plastering on the ground floor
Week 36, Day 2

Week 36, Day 2

Starting the dry-lining of the sloping ceiling over the Master Bedroom

Starting the dry-lining of the sloping ceiling over the Master Bedroom

Base coat of plaster on the curved roof over the staircase

Base coat of plaster on the curved roof over the staircase

One of the "Fylo" recessed strip lights boarded in place and ready for the skim coat

One of the “Fylo” recessed strip lights boarded in place and ready for the skim coat

Week 36, Day 1

Week 36, Day 1:

  • A site meeting with the Architect to agree the revised specification for the Zinc Roof and its Structured Underlay
    • This is now agreed but Full Metal Roofing need to finish another large project first so they won’t be starting work for a couple of weeks
  • More progress on the plastering, finishing off the walls in the Office and other areas on the Second Floor
  • More progress on the Plant Room pipework
  • The tele-handler was off-hired
Week 36, Day 1

Week 36, Day 1

Plaster skim coat complete on the walls in the Office

Plaster skim coat complete on the walls in the Office

Alcove in the Second Floor Bathroom

Alcove in the Second Floor Bathroom

Concealed cistern in the Master Bedroom En-Suite

Concealed cistern in the Master Bedroom En-Suite