Week 35, Day 5

Week 35, Day 5:

  • The “south” camera has been going offline occasionally (maybe it’s all the rain?) and as a result there are no time-lapse photos from that camera today, so here’s one from the “north” camera instead
  • More plastering on the Second Floor, including skimming the ceiling in the Office
  • More progress with the pipework for the Ground Source Heat Pump in the Plant Room
Week 35, Day 5

Week 35, Day 5

Plaster skim coat complete on the Office ceiling

Plaster skim coat complete on the Office ceiling

Pipework progressing in the Plant Room

Pipework progressing in the Plant Room

Week 35, Day 4

Week 35, Day 4:

  • Completion of the timber structure for the TV alcove in the Living Room
  • Sealing the masonry external walls in the Kitchen with a parge coat before installing the timber structure to hide the steel beams and soil pipes
Week 35, Day 4

Week 35, Day 4

The TV alcove now has its top and bottom

The TV alcove now has its top and bottom

Parge coat on the masonry walls in the kitchen, before the timber framework goes on

Parge coat on the masonry walls in the kitchen, before the timber framework goes on