Week 34, Day 5

Week 34, Day 5:

  • Some very heavy rain showers, hence the generally-damp look and the muddy puddles
  • The Ground Source Heat Pump and its accompanying tanks were delivered ready for installation next week
  • Some more electrical first-fix, mostly low-voltage cabling to the LED down-lighters from their (remote) drivers
  • Battening out the Master Bedroom walls and (sloping) ceiling ready for plasterboard – see photos below
Week 34, Day 5

Week 34, Day 5

"3x2" battens on the sloping ceiling of the master bedroom

“3×2” battens on the sloping ceiling of the Master Bedroom

The battens on the ceiling need to provide clearance for some low-profile downlighters.

Slim battens on the north wall of the Master Bedroom

Slimmer battens on the north wall of the Master Bedroom

Week 34, Day 4

Week 34, Day 4:

  • Back with the regular daily photos today, albeit a little later in the day than usual
  • Good progress with the plaster-boarding, preparing for the skim coat on the second floor
Week 34, Day 4

Week 34, Day 4

Ready for the skim coat in the second floor bathroom

Ready for the skim coat in the second floor bathroom

Plasterboard completed on the curved roof over the staircase

Plasterboard completed on the curved roof over the staircase