Week 51, Day 4

Week 51, Day 4:

  • Installing the remaining inspection chambers, connecting up the drains and supporting them in concrete so they stay in position during back-filling of the trenches
  • Finishing touches on the Ground Source Heat Pump installation, insulating the remaining fittings and topping up the brine circuit after it’s been running for a while and the automatic air vents have bled out most of the air (with a consequent reduction in operating pressure)
Week 51, Day 4

Week 51, Day 4

Drains to the west of the house

Drains to the west of the house

Drains to the east of the house

Drains to the east of the house

Week 51, Day 3

Week 51, Day 3:

  • Various bits of sealing and other preparations for the next air tightness test – not much to see so no extra photos today
  • I put the headline week counter (Week 51, Day 3) on pause for the Christmas break so today is actually the one-year anniversary of the start of the build – see here for the original post
Week 51, Day 3

Week 51, Day 3