Week 52, Day 4

Week 52, Day 4:

  • The first-floor balcony is now nearing completion, with the team from Alvaston Glass installing the three glass balustrade panels which fitted perfectly – just the floor tiles and their underlay to go
  • More preparation for the installation of the stair boxes, machining out the fixing holes in the ends of the steel treads where those had been adjusted
  • Some more finishing off elsewhere, including some boxing-in around a vent pipe in the second-floor bathroom
Week 52, Day 4

Week 52, Day 4

Glass panels installed on balcony

Glass panels installed on balcony