Week 52, Day 2

Week 52, Day 2:

  • Patching the holes in the plasterboard made when adjusting the staircase treads
  • Delivering a batch of the oak boxes for the stair treads
  • Insulating the rest of the duct work in the Plant Room
Week 52, Day 2

Week 52, Day 2

Oak boxes for stair treads stacked in hallway

Oak boxes for stair treads stacked in hallway

MVHR supply duct work now fully insulated in Plant Room

MVHR supply duct work now fully insulated in Plant Room