Week 54, Day 2

Week 54, Day 2:

  • Installation of the Phone Line into the house, using the armoured cable previously routed from the Comms room to the underground joint box outside
    • This isn’t operational yet due to a fault on the line between the Distribution Point and the Cabinet which should be fixed within a day or two
  • Laying the rubber tiles over their underlay on the balcony
    • These are Eurodec Premier Rubber Tiles in grey which protect the Sarnafil single-ply membrane beneath while allowing water to drain though
Week 54, Day 2

Week 54, Day 2

Eurodec Premier Rubber Tiles on balcony floor

Eurodec Premier Rubber Tiles on balcony floor

Week 54, Day 1

Week 54, Day 1:

  • More progress finishing off various small jobs
    • Fitting the stainless steel handrails on the wall side of the staircases
    • Boxing in the waste pipes in the Dressing Room
Week 54, Day 1

Week 54, Day 1

Boxing-in in Dressing Room

Boxing-in in Dressing Room