Week 68, Day 2

Week 68, Day 2:

  • More work on the door canopies, preparing to install the permanent waterproof membranes in place of the temporary polythene sheeting
  • Further progress on the preparations for the 14 low-level outside lights, which will be mounted on top of the stone cladding with their cables hidden within the cladding
Week 68, Day 2

Week 68, Day 2

Wiring for 1 of 14 outside wall lights (Nordlux Canto)

Week 68, Day 1

Week 68, Day 1:

  • The main event of the day was the delivery of the sandstone cladding, in a why-did-you-send-such-a-big-lorry lorry
Week 68, Day 1

Week 68, Day 1

Five pallets of real sandstone cladding pieces

A nicely-executed three-point-turn from the delivery driver