Not much visible progress evident in the photo, but there was a delivery of dry-mix concrete which got carefully loaded into the wall cavity below DPC, and the start of more excavation around the site.

Not much visible progress evident in the photo, but there was a delivery of dry-mix concrete which got carefully loaded into the wall cavity below DPC, and the start of more excavation around the site.

More of the same as yesterday, finishing up the below-DPC walling on the garages, off to the left of the overview shot.
The large digger and dumper used previously had been collected a few days ago, but a smaller digger and dumper were delivered since there’s a bit more excavation required around the outside of the walls to provide a good base for the scaffolding – and there is a layer of stone to be spread and compacted as a base for the insulation under the floor slabs.