No work on site today since it’s the Good Friday Public Holiday, but leaving this photo in place to show how the floor slab is curing (it’s a bit paler than yesterday).

No work on site today since it’s the Good Friday Public Holiday, but leaving this photo in place to show how the floor slab is curing (it’s a bit paler than yesterday).

Most of today was spent removing another 200-300mm of soil from the ‘courtyard’ between the house and the outbuildings, since that will later be landscaped with paving and planting beds – and will end up around 150mm lower than the internal floor slabs.
It’s now clear that it won’t be practical to redistribute all the excavated soil on-site so some of that will start being removed off-site, starting next week.