The floor laying team were back to finish off the waterproof vinyl flooring in the Utility Room and Shower Room, with most of the time spent welding the seams between the vinyl sheets. That clears the way to finishing off the Shower Room – fitting the sanitary ware and checking the foul drainage connections.
There was also a site visit by the Architect to prepare an initial snagging list and a separate visit by the Building Control officer.