The zinc around the Living Room window is now finished. It looks very shiny compared to the rest of the roof but it should weather down in a few weeks.
Week 81, Day 1
Completed zinc cladding for the Living Room window
No further progress on the zinc around the windows; not sure if that was because of the heavy rain in the morning or if the team had other commitments. Now expecting that to be finished early next week.
The Final Certificate from MFA Building Control arrived in yesterday’s post, following a final inspection a couple of weeks ago and some follow-up paperwork to show evidence that the electrical, ventilation and heating systems had all been signed off.
While the building is now officially Complete from a Building Regulations standpoint (the unfinished zinc around the windows doesn’t affect that) there will be a separate certificate from the Architect when all of the work within the scope of the build contract is completed (and then a further certificate when all evident defects have been addressed).
One of the key things triggered by the Building Regulations Final Certificate is the 3-month window for the VAT reclaim on eligible items which were not zero-rated at source – seeĀ https://www.gov.uk/vat-building-new-home