Outbuildings: Week 38, Day 3

Outbuildings: Week 38, Day 3

Another frosty night followed by a bright and sunny day, so still some frost visible on the Utility Room roof at noon (despite finding the loft insulation is mostly missing in there and needs to be topped-up).

Good progress on the rainwater attenuation pond:

  • Levelling out the bottom so that – if anything – water will pool at the outlet end, whereas it has been tending to pool at the inlet end
  • Installing the ‘swale inlet’ to calm the flow of water entering the pond, reducing the risk of erosion of the soil at the bottom of the pond in high-flow conditions
  • Installing the silt trap that will help prevent silt entering the pond – containing a ‘bucket’ that will need emptying periodically
  • Connecting to the upstream drainage pipework

The commissioning of the air-to-air heat pump is now mostly complete and all but one of the CCTV cameras are now operational. (The last camera will go up after the handrail for the external staircase gets installed, hopefully within the next week.)

Outbuildings: Week 35, Day 5

Outbuildings: Week 35, Day 5

Another day of good progress, with two of the garage door roller shutters now fully operational and another one well on the way. That and the last one should be finished on Monday.

The team from Chellaston Renewables were back on site to fit the external heat pump unit on its wall bracket – not a simple task since it weighs over 60kg, and it’s quite a way off the ground.

External unit for Daikin Air-to-Air heat pump installed on East wall of Workshop