Week 4, Day 5

Week 4, Day 5:

  • More progress on the below-ground cavity walls.
  • Initial preparation for attaching the steelwork to the foundations by drilling holes in the concrete.
  • A site visit from Western Power Distribution (the electricity DNO for the area) to assess the condition of the overhead supply cables and poles and to fit a data logger to capture voltage and current snapshots during the coming week.
    • The proposed make and model of Ground Source Heat Pump (a NIBE F1145) has a compressor start-up current of 32A which is just over the limit for some of the existing overhead cables. The data logger will highlight if there are any issues with the cables which mean they need maintenance work anyway; if they do that will (hopefully) reduce the contribution I need to make to having the cables upgraded.
  • A new delivery of building sand for the block laying mortar since the previous supply was too coarse. The old sand will get used for filling in around the GSHP collector pipes.
Week 4, Day 5

Week 4, Day 5

Voltage and Current data logger connected to electricity supply in GRP cabinet

Voltage and Current data logger connected to electricity supply in GRP cabinet

Week 4, Day 3

Week 4, Day 3:

  • Completing the removal of the excess soil from around the foundations.
  • Moving some of the concrete blocks into position near the foundations ready for installation.
  • Insulating the GSHP pipes where they start running closer together under the house (to help prevent the water coming from the ground loops being chilled by the flow from the house).
  • Delivery of the four rolled steel columns which will bolt to the foundation concrete and help support the south side of the house.
  • More clearing of the rubble around the old outbuildings.
Week 4, Day 3

Week 4, Day 3

Blocks stacked ready for installation

Blocks stacked ready for installation

Insulation around 50mm GSHP pipes

Insulation around 50mm GSHP pipes