Week 54, Day 4

Week 54, Day 4:

  • Fitting the “secret” door to the electrical cupboard in the kitchen
  • Installing the wooden threshold strips by the sliding doors on the Ground Floor
  • Installing some of the stair tread end caps
  • Installing the outside taps
Week 54, Day 4

Week 54, Day 4

"Secret" door to electrical cabinet in kitchen

“Secret” door to electrical cabinet in kitchen

Oak caps on ends of stair treads

Oak caps on ends of stair treads

Week 49, Day 3

Week 49, Day 3:

  • Almost completed on the Ground Source Heat Pump commissioning – all powered up and heating water with just a bit more insulation to finish off
  • Installing the hand rail for the balcony, ready for the glass balustrade
  • More second-fix electrical, connecting up the electric windows on the second floor and more of the wall lights
Week 49, Day 3

Week 49, Day 3

Handrail installed for balcony; just the glass to go

Handrail installed for balcony; just the glass to go

Electric clerestory windows on the second floor

Electric clerestory windows on the second floor

Master bedroom wall lights when illuminated

Master bedroom wall lights when illuminated