Week 40, Day 1

Week 40, Day 1:

  • Installing the painted aluminium channels over the wooden posts between the clerestory windows and also the aluminium window cills, now the zinc roofing has been completed at the top of the south roof
  • More work on the zinc roofing – the fiddly bits around the edges take much longer than the large flat areas
  • More plastering, mainly in the open plan kitchen – getting that ready for the kitchen units (due next week)
  • Making up some corner caps out of cedar boards to finish off the external corners on the cedar-clad areas
Week 40, Day 1

Week 40, Day 1

Aluminium channels over insulation covering the posts between the clerestory windows

Aluminium channels over insulation covering the posts between the clerestory windows

Skimmed plasterboard ceiling in kitchen

Skimmed plasterboard ceiling in kitchen

Fabricating caps for the external corners on the cedar-clad areas

Fabricating caps for the external corners on the cedar-clad areas

Week 35, Day 1

Week 35, Day 1:

  • Lots more rain
  • The main event for the day was the installation of the “missing” window on the second floor and the replacement of the two windows originally made with the wrong colour frames
  • More electrical first-fix
  • Installing some of the contoured panels for the LED strip lights recessed into the ceiling
Week 35, Day 1

Week 35, Day 1

Lifting the glass for the Office window up to the second floor

Lifting the glass for the Office window up to the second floor

Office window installed on the second floor

Office window installed on the second floor

"Fylo" lighting channel installed in the ceiling - needs another layer of plasterboard to bring it flush

“Fylo” lighting channel installed in the ceiling – needs another layer of plasterboard to bring it flush