Week 38, Day 1

Week 38, Day 1:

  • I didn’t spot the disk on the Raspberry Pi computer which grabs the hourly snapshots went full at noon so the evening shots are missing and hence the automated Posting logic didn’t work properly. The photo here is from 12:39 – not even on the hour. Should all be fixed now.
  • More electrical first-fix – installing the remaining plaster light housings in the kitchen and preparing some trunking for the incoming mains cable.
  • More plastering, boarding out the stud-work in the open plan area.
  • Some more joinery – such as installing the door frames (which have been going in over recent days but without any photos until now)
Week 38, Day 1

Week 38, Day 1

Plaster ceiling light fittings over the kitchen sink

Plaster ceiling light fittings over the kitchen sink

Plasterboard in the south-west corner of the open plan area

Plasterboard in the south-west corner of the open plan area

Door frame - this one is between the Kitchen and the Utility Room

Door frame – this one is between the Kitchen and the Utility Room

Week 37, Day 5

Week 37, Day 5:

  • More plastering
  • A bit of plumbing first-fix
  • More electrical first-fix, mainly sockets and the ceiling lights on the ground floor
Week 37, Day 5

Week 37, Day 5

Recessed plaster downlight housings in kitchen

Recessed plaster downlight housings in kitchen

Finished dropped ceiling in Bedroom 2 En-Suite

Finished dropped ceiling in Bedroom 2 En-Suite