Week 21, Day 2

Week 21, Day 2:

  • Starting to round out the curved section of roof
  • The SIPS panels are planar and form a series of facets rather than a true curve
  • The finished curve is formed using 3 layers of 6mm plywood, glued together
Week 21, Day 2

Week 21, Day 2

Starting to install the first layer of 6mm plywood on the curved section of the roof

Starting to install the first layer of 6mm plywood on the curved section of the roof

Week 21, Day 1

Week 21, Day 1:

  • Completion of the flat boarding over the vertical section of “roof” over the north elevation of the first floor
Week 21, Day 1

Week 21, Day 1

Completing the lower section of "roof" over the first floor

Completing the lower section of “roof” over the first floor

Completed lower section of "roof" cladding

Completed lower section of “roof” cladding

Framing for side and end of "roof" over first floor

Framing for side and back of “roof” over first floor