Week 36, Day 4

Week 36, Day 4:

  • More electrical first-fix
  • More plastering, mostly on the first floor landing (which joins the second floor landing on one side)
Week 36, Day 4

Week 36, Day 4

Galvanized steel back-box for DRACO plaster wall light, with electrical connection box above

Galvanized steel back-box for DRACO plaster wall light, with electrical connection box above

DRACO plaster wall light in-situ on first floor landing

DRACO plaster wall light in-situ on first floor landing

 

Week 36, Day 3

Week 36, Day 3:

  • More plasterboard dry-lining
  • More skimming of the plasterboard on the second floor (notably the curved roof over the staircase)
  • Building out the wooden framework for the south wall in the open-plan area
  • More electrical first-fix, mostly the recessed wall lights in the hall and landing
Week 36, Day 3

Week 36, Day 3

Dry lining in the family bathroom

Dry lining in the family bathroom

Completed plaster skim coat over the staircase

Completed plaster skim coat over the staircase

Timber framework on the south wall of the open plan area

Timber framework on the south wall of the open plan area