Outbuildings: Week 36, Day 1

Outbuildings: Week 36, Day 1

Still awaiting news on the manufacture of the replacement concrete headwall so no progress from the main build team today. There was however another monthly site meeting with the Architect and the Main Contractor to review status and value the work completed to date, for the next monthly stage-payment.

The team from Attenborough Doors were back to complete the installation of the roller shutters. They mostly finished the final door but got called away to an emergency repair mid-afternoon so will return in the morning to finish things up.

One of the four Hormann RollMatic 2 roller shutter doors, viewed from the inside

Commissioning of the data networking and home automation systems is progressing, with the local KNX installation in the Outbuildings now operational in a standalone fashion – so the light switches work but it’s not yet possible to control the lights from the House or using Home Assistant.

The block paving blocks were also delivered direct from the manufacturer in Yorkshire, ready for installation in a few days’ time. These are Plasmor Sorrento Permi-8 permeable paving blocks. There is a limited choice of colours for the permeable blocks and ‘Sarsen Stone’ seemed the least-bad option to blend with some other stone on the site. The area by the Garages needs 23 packs, and there were 26 packs for a full lorry-load so the extra 3 will be stored and used to extend the paving towards the house – once the extent of that paving is confirmed.

Block Paving Blocks delivered ready for installation later in the week