The main build team were on site all day sorting out a few of the smaller groundworks tasks:
- Finishing the installation of the last of the Marshalls GrassGuard blocks around the perimeter of the block-paved parking area
- There’s around 2/3 of a pack left over but those will be saved for future use
- Filling in the holes excavated to access the water mains and electrical ducts
- Clearing a trench around the foul drainage pipe that runs under what-will-be the vehicle access to the parking area, so that can be encased in concrete to maintain its level even with traffic passing relatively closely over the top of it

The right-sized replacement concrete headwall was allegedly due for delivery today but is now said to be coming tomorrow.