Outbuildings: Week 27, Day 3

Outbuildings: Week 27, Day 3

More work on the below-DPC elements of the external staircase, including its floor slab and the stainless steel ‘wall starter kit’ that will tie the new brickwork to the now-existing wall. Also preparation for the two ‘buttresses’ by the garage doors.

No scaffolders again so the usual on-site build team dismantled the rest of the scaffolding around the inside of the Courtyard (after the overview photo was taken).