Outbuildings: Week 30, Day 3

Outbuildings: Week 30, Day 3

No further work on the Courtyard today; that’s waiting for the rainwater harvesting tank which is due for delivery tomorrow. Good progress with the External Staircase, which needs the reconstituted stone steps before being taken further (and those are still being made).

The masonry for the external staircase completed as much as it can be until the reconstituted stone steps are available

The groundworks team swapped to working on the parking area to the North of the Garages, in preparation for that being block-paved.

Starting to bring the level of the parking area up with compacted crushed stone

The (surprisingly heavy) two-leaf ‘barn’ door was also installed into the frame that had been fitted the other day. That just leaves the Garage Door roller shutters, which are roughly a couple of weeks away.