The Utility Room and Shower Room ceilings received their plaster skim-coat, which was completed more quickly than the Workshop yesterday, with it being only about 1/4 the area.

Opening all the windows slightly helped to dry the plaster despite the cool temperature, high humidity and lack of wind outdoors.

A few more bits of underground drainage pipework outside then starting to clear the site of the rainwater attenuation pond and its outfall to the field drainage ditch. A couple more lorry-loads of muck-away, which cleared all the previously-excavated spoil. Digging out the pond will generate a bit more spoil, but the edges of the pond will need building up – and will need to be level.