Week 47, Day 4

Week 47, Day 4:

  • Quite a lot of time spent tidying and cleaning the rooms which are nearly finished
  • More second-fix electrical:
    • Work in the Plant Room, hooking up the supply to the Ground Source Heat Pump and the heating zone valves and circulation pumps
    • Work on the ground floor, wiring in the DALI-dimmable LED drivers for the kitchen and open plan dining area
Week 47, Day 4

Week 47, Day 4

Heating circulation pumps - pipes need insulating

Heating circulation pumps – pipes need insulating

BPM Aquilae lights in the Open Plan area

BPM AQUILAE lights in the Open Plan area

These lights are 9.6W LEDs running at 500mA constant current. The hole in the middle is for a ceiling loudspeaker.

Week 47, Day 3

Week 47, Day 3:

  • A bit more tiling – grouting the floor tiles in the ground floor shower room
  • Installing the control boards for the blinds and windows on the second floor, in the Plant Room
Week 47, Day 3

Week 47, Day 3

Grouted floor tiles in the ground floor Shower Room

Grouted floor tiles in the ground floor Shower Room

Control boards in the Plant Room

Control boards in the Plant Room