Week 48, Day 4:
- The team from Alvaston Glass were on-site for most of the day making templates for the tempered glass balustrades on the staircases and the balcony
- More second-fix electrical, with more installations in the Plant Room (notably the sub-meter for the Ground Source Heat Pump) and more LED drivers on the First Floor