Week 50, Day 3

Week 50, Day 3:

  • Having decided that the best way to get the Living Room ceiling flat and level was to replace the plasterboard using metal studs carefully levelled under the existing joists and then skim the new boards the old boards had to come down
  • The steel steps on the staircases that needed adjusting were re-welded
Week 50, Day 3

Week 50, Day 3

Living Room ceiling plasterboard removed in preparation for re-boarding

Living Room ceiling plasterboard removed in preparation for re-boarding

Steel steps re-welded

Steel steps re-welded