Week 46, Day 5

Week 46, Day 5:

  • More second-fix – door stops and some more lighting fixtures
  • More tiling – notably the wall tiles in the Ground Floor Shower Room
  • An initial air-tightness test which showed we’re a little short of the Passivhaus requirement of 0.6, with a reading of around 1, so some more work to do there
Week 46, Day 5

Week 46, Day 5

Wall tiles in the shower for the Ground Floor Shower Room

Wall tiles in the shower for the Ground Floor Shower Room

Air pressure test

Air pressure test