Week 48, Day 5

Week 48, Day 5:

  • More templating of the glass for the staircase – photo below
  • More second-fix electrical, installing and commissioning some more of the LED drivers
  • More work to complete the installation of the Ground Source Heat Pump, including installing the various temperature sensors (internal, external and on the hot water and heating buffer tanks)
Week 48, Day 5

Week 48, Day 5

Templates for the glass balustrade on the staircase

Templates for the glass balustrade on the staircase