Week 65, Day 5

Week 65, Day 5:

  • More work on the door canopies, mostly the side door since the front door is nearing completion
  • Installation of the flat panel lights in the ceilings of the door canopies, to illuminate the area outside the doors
Week 65, Day 5

Week 65, Day 5

Side door canopy with some of the cedar cladding installed

Front door canopy with light installed

15W LED flat panel over front door