Outbuildings: Week 20, Day 3

Outbuildings: Week 20, Day 3

The brickwork and blockwork is now finished – apart from the external staircase (which is being left until later) so the bricklaying team moved on to clearing away their equipment and the offcuts of bricks and blocks. Most of the mortar spills on the concrete floor have also been scraped off and swept clean and the timber formers for the shallow arches over the garage door openings have been removed. In parallel there’s been more progress with the feltting-and-battening, starting on the north-facing Garage roof.

Northern side of the Garages, with the arch formers removed and the start of the felt-and-battens on this section of roof