Week 45, Day 4

Week 45, Day 4:

  • MVHR commissioning by Steve from the Green Building Store, adjusting all the air valves to deliver the correct flow rates and setting the Low, Medium and High fan speeds
  • More second-fix on the intruder and fire alarm system, installing the control panel, keypad etc.
  • More second-fix electrical, including installing some of the wall lights
  • More work on the door furniture, including the lock on the Plant Room door
Week 45, Day 4

Week 45, Day 4

Intruder alarm box on the west elevation

Intruder alarm box on the west elevation

Week 45, Day 3

Week 45, Day 3:

  • Close to completion on the kitchen installation, with the hob now sealed to the Silestone worktop with heat-resistant silicone and the pop-up power sockets installed in the island worktop
  • The first day of second-fix on the security and fire alarm systems, installing some of the movement and shock sensors
  • More second-fix electrical, installing the last of the PIR sensors for the lights in some of the ground floor rooms
  • More work on the internal doors, drilling out for the door handles and latches
Week 45, Day 3

Week 45, Day 3

Second Floor Landing complete apart from paintwork

Second Floor Landing complete apart from paintwork and staircase balustrade

PIR movement sensor and shock sensor on door frame

PIR movement sensor and shock sensor on door frame