Week 58, Day 4:
- More work on the retaining wall, preparing for back-filling
- Installing the outside tap by the front steps, taking care with the pipe runs so this can be used to drain the water from all the outside pipework in winter
- Installing the perforated pipe in a layer of pea gravel
- Starting to back-fill the other sections with subsoil excavated previously