Week 5, Day 4

Week 5, Day 4:

  • Camera is working again (for now, after I turned it off and on again…) though not until after dark so the shot below is from Friday morning.
  • More progress on the under-floor cavity walls.
Week 5, Day 4

Week 5, Day 4

Under-floor cavity wall at north-east corner

Under-floor cavity wall at north-east corner

Week 5, Day 3

Week 5, Day 3:

  • More work to complete the concrete block cavity walls up to ground floor level, ready for the installation of the beam-and-block floor.
  • Two steel wind-posts added to the west wall, adding structural support around a tall, narrow window.

The main camera still isn’t working so here’s another photo from Steve taken on Thursday morning, showing the steelwork.

Week 5, Day 4

Week 5, Day 4

Wind posts

Rectangular Hollow Section steel wind-posts either side of tall, narrow window in the corner of the Living Room