Week 27, Day 3

Week 27, Day 3:

  • Installation of the Ecobead Platinum cavity wall insulation
  • The start of the preparation of the Western Red Cedar cladding boards
    • These get a coat of Osmo Clear UV-Protection Oil Extra (420 Clear Semi-Matt) before being installed
  • Completion of the external insulation on the gable walls of the Structural Insulated Panels
  • More first-fix of plumbing and electrical systems
Week 27, Day 3

Week 27, Day 3

Cavity Wall Insulation lorries

Cavity Wall Insulation lorries

Western Red Cedar timber cladding being prepared for installation

Western Red Cedar timber cladding being prepared for installation

Osmo UV Protection Oil

Osmo UV Protection Oil

Week 27, Day 2

Week 27, Day 2:

  • Some progress agreeing the precise specification of the membranes required to protect the zinc roof finish
    • In particular, confirmation that it will be necessary to use a completely vapour-tight barrier on the inside of the Structural Insulated Panels to prevent any moisture from inside the house reducing the life of the zinc or the OSB within the SIPs
    • ALUTRIX which is a combination of thick aluminium foil and bitumen looks like the best option – on a “warm roof” this needs to go on the inside, where it will also act as a really good air tight barrier
  • More first-fix of the plumbing and electrical systems
Week 27, Day 2

Week 27, Day 2