Week 24, Day 5

Week 24, Day 5:

  • The second day of window installation, though only really half a day because of waiting for a further delivery (now due on Monday)
  • More preparation of the plywood boxes for the external doors
Week 24, Day 5

Week 24, Day 5

View from main camera location, showing clerestory windows

View from main camera location, showing clerestory windows

One of the Living Room windows, incorrectly supplied in White rather than Dark Grey

One of the “temporary” Living Room windows, incorrectly supplied in White rather than Dark Grey