Week 25, Day 4

Week 25, Day 4:

  • First fix plumbing, installing the soil pipes and some of the hot water distribution system
  • Lots more work on the ground floor, laying the insulation and some of the pipework that needs to run within the insulation
Week 25, Day 4

Week 25, Day 4

First-fix plumbing in Plant Room

First-fix plumbing in Plant Room